Raypak Y-200 Series Manuale Utente Pagina 4

  • Scaricare
  • Aggiungi ai miei manuali
  • Stampa
  • Pagina
    / 8
  • Indice
  • SEGNALIBRI
  • Valutato. / 5. Basato su recensioni clienti
Vedere la pagina 3
Y-200 LonWorks Module Installation and Operating Manual
2
Installation
1. Turn off the power to the Y-200.
2. Open the front cover of the Y-200.
3. Open the “Display and Keypad” door to gain
access to the Y-200 Control Board and Lon-
Works Module mounting location.
4. Plug LonWorks Module onto the P1 & P2 con-
nectors on the Y-200 Control Board. (See dia-
gram below.)
5. Connect communication cabling to the 2-pin
connector J13 (LonWorks connection). (See dia-
gram below.)
6. Install conduit as appropriate for connection of
communication cabling.
For LonWorks Communications
Cabling
Use cable and installation techniques as specified in
the LonWorks controller documentation.
Y-200 Control Board
P1
P2
Service Switch
J13
SW2
Reset
Switch
SW1 Service
Switch
Vedere la pagina 3
1 2 3 4 5 6 7 8

Commenti su questo manuale

Nessun commento